The below Fact Sheets, Frequently Asked Questions (FAQs) and Fast Facts provide more information about the Miriam Vale BESS and Solar Farm. See the Miriam Vale Solar Farm website for more specific information about that project.
Project planning
The Miriam Vale BESS and Solar Farm Development Applications (DAs) were lodged with Gladstone Regional Council (GRC) in mid-2024. Documents submitted with the BESS DA are included below.
As a result of listening to community feedback, we have changed the scale and design of the projects significantly since the DAs were lodged. Based on these changes, and the new Planning (Social Impact and Community Benefit) and Other Legislation Amendment Bill 2025, these DAs are likely no longer relevant. PEP therefore withdrew the DAs on Friday, 13 June, and is finalising updated planning and design, and assessing resubmission via the appropriate approval authority. You can read the BESS DA withdrawal notice here.